Dear All
Recently, we have many wells where the high pressure of gas in the casing pipes have been observed which stops the oil production.,
In order to restart the well, high casing pressure is released and then production from well starts.
For this reason, auto relieve valves have been installed initially for three wells, theses auto relieve valves derive direct the gas to the flow line in order to prevent environmental pollution and hazards location. But gas in the flow line make the system two phase flow and affect the functionning of micro motion meter installed in the OGM.
Based on your experience What is the best solution? and what is the best software for well simulation from bottom hole to well head with High GOR?
Many thanks
-------------------------------------------
Bassem Balghouthi
Flow Assurance Engineer
EPPM
Tunisia
-------------------------------------------