Good day Well Integrity practitioners,
Looking forward to obtain your experience and opinion on resolving plugged downhole capillary lines.
The lines were intended to use for pumping of corrosion inhibitor, however after 2 months of pumping corrosion inhibitor chemical to downhole it was identified that all wells capillary lines are plugged. The plugging fact was confirmed by applying positive pressure into the line and no PFO observed.
Thanks in advance for your feedbacks.
Regards,
Tural