Lajpat,
I assume that you have the details of the risk analysis from the initial concept selection. Ideally, that should have been the best time to discuss the risks and mitigations and if required, a change in the completion design.
The ideal way of producing the two formations would have been either using dual string - the shorter string producing from the shallower formation and the long string from deeper formation. Assuming that it is not possible due to restriction of tubing size or flow rates (not mentioned in your query), the alternate completion method should have been commingled flow through the tubing with packers isolating the shallow zone and flow through SSD or FCV in the tubing.
With the current scenario mentioned by you, the primary concern will be the safety barriers on the casing side.
It seems that the well is not flowing now and based on the information available, I will suggest to have commingled flow through tubing as mentioned earlier in my response, if still possible.
Out of curiosity, can you specify where the flow is comingled, the downhole temperatures and the expected flow rates? I assume that the well is located onshore.
------------------------------
Sudeep Roy
Oil & Gas Professional
Geneve
------------------------------